Resume: We can analyse the implementation of infrastructure projects based on the budget execution figures of the Ministry of Regional Development and Infrastructure.

The 2020 budget of the Ministry of Regional Development and Infrastructure is GEL 2.071 billion. The Ministry’s first quarter plan for 2020 was GEL 408.078 million whilst the execution figure was GEL 433.9 million. Therefore, the Ministry’s first quarter plan was executed by 106.3%. In addition, almost all plans of the programs carried out by the Ministry ended in surplus. The first quarter plan of a large infrastructure project – certain sections of the high-speed highway – was also executed by nearly 100%. However, Zaza Gabunia made his statement on 22 April 2020 at the plenary session of the Parliament of Georgia and April data will be reflected in the second quarter figures. Moreover, the state of emergency was declared in Georgia on 21 March 2020 and the impact of the pandemic on project implementation will also become clearer in the second quarter of 2020. Given all of the aforementioned factors, FactCheck leaves the statement without a verdict.

Analysis

The Chairperson of the Regional Policy and Local Self-Governance Committee of the Parliament of Georgia, Zaza Gabunia, stated at the plenary session of the Parliament of Georgia: “None of the large infrastructure projects have been stopped.”

We can analyse the implementation of infrastructure projects based on the budget execution figures of the Ministry of Regional Development and Infrastructure.

The 2020 budget of the Ministry of Regional Development and Infrastructure is GEL 2.071 billion. The Ministry’s first quarter plan for 2020 was GEL 408.078 million (the budget is planned by quarters which means that only the first quarter budget’s execution figures are currently available) whilst the execution figure was GEL 433.9 million. Therefore, the Ministry’s first quarter plan was executed by 106.3%.

Table 1: Separate Infrastructure Programme Budget Execution Figures in the First Quarter of 2020

Programme

Plan

Fact

Execution (%)

Improvement of Road Infrastructure

295.452

302.206

102.3

High-Speed Highway

217.92

224.931

103.2

Restoration of Water Infrastructure

45.454

61.308

134.8

Restoration of Regional and Municipal Infrastructure

41.428

44.668

107.8

Solid Waste Management

7.917

8.01

101.2

Support of Internally Displaced Persons

5.301

5.301

100

Rehabilitation of General Education Infrastructure

11.005

10.966

99.6

Source: State Treasury

According to the official data, almost all of the plans of the programs carried out by the Ministry of Regional Development and Infrastructure ended in surplus. The only exception is the rehabilitation of the general education infrastructure programme where execution slightly lags behind.

The first quarter budget execution figures of investment projects carried out by 2020 state budget donors; in particular, for certain sections of the high-speed highway were as follows:

Section

Plan

Fact

Execution (%)

Agara-Zemo Osiauri

284,000

281,000

98.9

Zemo Osiauri-Rikoti

12.590 million

12.579 million

99.9

Samtredia-Grigoleti

17.775 million

17.737 million

99.8

Batumi’s new bypass road

16.857 million

21.660 million

128.5

Chumateleti-Khevi

1.454 million

1.437 million

98.8

Khevi-Ubisa

23.630 million

23.613 million

99.9

Ubisa-Shorapani

18.100 million

18.087 million

99.9

Shorapani-Argveta

87.805 million

90.227 million

102.8

Zestaponi-Kutaisi-Samtredia

4.262 million

4.236 million

99.4

Kobuleti’s new bypass road

2.180 million

2.102 million

96.4

Source: State Treasury

As illustrated by the figures, there are full budget executions in almost all ongoing sections of the high-speed highway and there are also surplus executions for two sections.

However, in order to analyse the continuity of the implementation of infrastructure projects by the end of April (the statement was made on 22 April 2020 at the plenary session of the Parliament of Georgia), it would be appropriate to wait for the second quarter execution figures. Of additional note is that on 21 March 2020 Georgia declared a state of emergency because of the coronavirus pandemic. The state of emergency did not impose restrictions on infrastructure projects and companies were allowed to carry out work in compliance with safety rules and the recommendations issued by the Georgian Ministry of Healthcare. Although, restrictions were imposed on the production of building materials, these restrictions were lifted on 5 May 2020. The lifting of the restrictions does not apply to the trade of building materials and only online purchase is allowed. The experience of the past years when the implementation of large infrastructure projects (in particular, the construction of certain sections of the high-speed highway) were hampered and project deadlines were often not met (see: article 1, article 2) also needs to be taken into account. Given all of the aforementioned, we will be able to see the clear picture of how infrastructure projects were carried out during the pandemic in the second quarter of 2020. FactCheck will continue to keep an eye on the implementation of infrastructure projects and provide our readers with updated information.